Reconstruction of SS 150 kV «Bogdanivska» for issue station power of «Pokrovska SES»

Project features

Task:

Accomplishment of reconstruction of SS 150/35/6 kV «Bogdanivska» for organization of scheme for issue of power of «Pokrovska SES»

Customer:

DTEK DNIPRO GRIDS JOINT-STOCK COMPANY

Period of work:

May 2019 – September 2019

Place of work:

Pokrov city, Dnipro region

Project description

Company Elmico LLC in accordance with subcontract with the general contractor TAVRIDA ELECTRIC DNEPR LLC completed the reconstruction of 150 kV grid cells of the 150/35/10 kV “Bogdanivska” of DTEK DNIPRO GRIDS JOINT-STOCK COMPANY, with the aim to connect Pokrovska SES solar power station to the Ukrainian energy system.

The construction of a new 150 kV cell was completed with regard to the construction of foundations and installation of high-voltage equipment from foreign and domestic manufacturers. Primary equipment for high-frequency communication was installed, reconstruction of existing cable channels and installation of power and control cables were carried out, protection and automation cabinets were mounted.