Participation in project on reconstruction of the 750 kV SS “Kyivska”. The second phase.

Project features

Task:

Installation and commissioning of the main primary equipment 330 kV, installation of cabinets for outdoor installation and preparation of the construction part of cable routes.

Customer:

“HOROS” LLC

Period of work:

May 2017 — December 2017

Place of work:

Makarovsky village, Kyiv district

Project description

Elmico LLC in accordance with the subcontract took part in reconstruction of the 750kV substation “Kyivska” of the Central Electric Power System of the State Electric Power Company “Ukrenergo”.  

Our company’s specialists performed installation and commissioning of 330 kV SF6 circuit breakers and 330 kV current transformers manufactured by ABB, ALSTOM manufactured 330 kV disconnectors,  cabinets for outdoor installation SHPV, SHUV, PDS, Shur, NW-60, for the preparation of cable lines – installation concrete trays and the device of cable pits and cable crossings over roads, drainage channels and crossings through cable trays. The work was carried out in accordance with the project documentation  in compliance with building codes and regulations, with the proper quality and on time.